In September 2011, ETP filed suit against us and a third party in connection with the cancelled project alleging, among other things, that we and ETP had formed a “partnership.”  The case was tried in the District Court of Dallas County, Texas, 298th Judicial District.  While we firmly believe, and argued during our defense, that no agreement was ever executed forming a legal joint venture or partnership between the parties, the jury found that the actions of the two companies, nevertheless, constituted a legal partnership.  As a result, the jury found that ETP was wrongfully excluded from a subsequent pipeline project involving a third party, and awarded ETP $319.4 million in actual damages on March 4, 2014.  On July 29, 2014, the trial court entered judgment against us in an aggregate amount of $535.8 million, which included (i) $319.4 million as the amount of actual damages awarded by the jury, (ii) an additional $150.0 million in disgorgement for the alleged benefit we received due to a breach of fiduciary duties by us against ETP and (iii) prejudgment interest in the amount of $66.4 million.  The trial court also awarded post-judgment interest on such aggregate amount, to accrue at a rate of 5%, compounded annually.

We filed our Brief of the Appellant in the Court of Appeals for the Fifth District of Dallas, Texas on March 30, 2015 and ETP filed its Brief of Appellees on June 29, 2015.  We filed our Reply Brief of Appellant on September 18, 2015.  Oral argument was conducted on April 20, 2016, and the case was then submitted to the Court of Appeals for its consideration.  On July 18, 2017, a panel of the Court of Appeals issued a unanimous opinion reversing the trial court’s judgment as to all of ETP’s claims against Enterprise, rendering judgment that ETP take nothing on those claims, and affirming Enterprise’s counterclaim against ETP of approximately $0.8 million, plus interest.

On August 31, 2017, ETP filed a motion for rehearing before the Dallas Court of Appeals, which was denied on September 13, 2017.  On December 27, 2017, ETP filed its Petition for Review with the Supreme Court of Texas.  As of December 31, 2017, we have not recorded a provision for this matter as management continues to believe that payment of damages by us in this case is not probable. We continue to monitor developments involving this matter.

PDH Litigation

In July 2013, we executed a contract with Foster Wheeler USA Corporation (“Foster Wheeler”) pursuant to which Foster Wheeler was to serve as the general contractor responsible for the engineering, procurement, construction and installation of our PDH facility.  In November 2014, Foster Wheeler was acquired by an affiliate of AMEC plc to form Amec Foster Wheeler plc, and Foster Wheeler is now known as Amec Foster Wheeler USA Corporation (“AFW”).  In December 2015, Enterprise and AFW entered into a transition services agreement under which AFW was partially terminated from the PDH project.  In December 2015, Enterprise engaged a second contractor, Optimized Process Designs LLC (“OPD”), to complete the construction and installation of the PDH facility.

On September 2, 2016, we terminated AFW for cause and filed a lawsuit in the 151st Judicial Civil District Court of Harris County, Texas against AFW and its parent company, Amec Foster Wheeler plc, asserting claims for breach of contract, breach of warranty, fraudulent inducement, string-along fraud, gross negligence, professional negligence, negligent misrepresentation and attorneys’ fees.  We intend to diligently prosecute these claims and seek all direct, consequential, and exemplary damages to which we may be entitled.

Environmental Matters

On occasion, we are assessed monetary sanctions by governmental authorities related to administrative or judicial proceedings involving environmental matters.  We do not expect such expenditures to be material to our consolidated financial statements.

§
In January 2015, the Attorney General of Texas filed litigation against us for CAA violations resulting from the February 2011 NGL release and fire at the West Storage location of our Mont Belvieu, Texas underground storage facility. Resolution of these matters is expected to result in monetary sanctions in excess of $0.1 million.

§
In December 2017, we received a Notice of Enforcement from the Texas Commission on Environmental Quality associated with historical self-disclosed violations that occurred at our Mont Belvieu complex.  The eventual resolution of these matters may result in monetary sanctions in excess of $0.1 million.